Effective December 3 - NetApp adopts Microsoft’s Business-to-Customer (B2C) identity management to simplify and provide secure access to NetApp resources. For accounts that did not pre-register (prior to Dec 3) access to your NetApp data may take up to 1 hour as your legacy NSS ID is synchronized to the new B2C identity. To learn more, Read the FAQ and Watch the video. Need assistance? Complete this form and select “Registration Issue” as the Feedback Category. 
NetApp Knowledge Base

What is the procedure to gracefully shutdown and power up your storage system during a scheduled power outage?

Views:
56,433
Visibility:
Public
Votes:
14
Category:
ontap-9
Specialty:
hw
Last Updated:

Applies to

  • AFF Systems
  • FAS Systems
  • ASA Systems
  • MetroCluster FC
  • MetroCluster IP
  • ONTAP 9
  • Data ONTAP 8 7-Mode
  • E-Series
  • NetApp HCI

Questions

  • What is the order to power elements up and down during a power cycle procedure?
  • What is the procedure to gracefully shutdown and power up your storage system during a scheduled power outage?
  • What is the procedure to power off a storage system?

Answer

Before you start
ONTAP 9
Configuration Procedure
High Availability (HA) pairs (AFF, ASA and FAS Systems) How to perform a graceful shutdown and power up of ONTAP storage systems
High Availability (HA) pair in a 4+ node cluster How to perform a graceful shutdown and power up of one HA pair in a 4+ node cluster
MetroCluster FC Powering off an entire MetroCluster FC configuration
MetroCluster IP Powering off an entire MetroCluster IP configuration
ONTAP 8 (7-mode)
Configuration Procedure
High Availability (HA) pair How to perform a graceful shutdown and power up of Data ONTAP 8.2 (7-mode) storage system
E-Series
Configuration Procedure
All E-Series platforms How to power off an E-Series storage system
NetApp HCI system
Configuration Procedure
NetApp HCI How to power off and power on a NetApp HCI system