What is the procedure to gracefully shutdown and power up your storage system during a scheduled power outage?

Views:
49,138
Visibility:
Public
Votes:
8
Category:
ontap-9
Specialty:
hw
Last Updated:

Applies to

  • AFF Systems
  • FAS Systems
  • ASA Systems
  • MetroCluster FC
  • MetroCluster IP
  • ONTAP 9
  • Data ONTAP 8 7-Mode
  • E-Series
  • NetApp HCI

Questions

  • What is the order to power elements up and down during a power cycle procedure?
  • What is the procedure to gracefully shutdown and power up your storage system during a scheduled power outage?
  • What is the procedure to power off a storage system?

Answer

Before you start
ONTAP 9
Configuration Procedure
High Availability (HA) pairs (AFF, ASA and FAS Systems) How to perform a graceful shutdown and power up of ONTAP storage systems
High Availability (HA) pair in a 4+ node cluster How to perform a graceful shutdown and power up of one HA pair in a 4+ node cluster
MetroCluster FC Powering off an entire MetroCluster FC configuration
MetroCluster IP Powering off an entire MetroCluster IP configuration
ONTAP 8 (7-mode)
Configuration Procedure
High Availability (HA) pair How to perform a graceful shutdown and power up of Data ONTAP 8.2 (7-mode) storage system
E-Series
Configuration Procedure
All E-Series platforms How to power off an E-Series storage system
NetApp HCI system
Configuration Procedure
NetApp HCI How to power off and power on a NetApp HCI system

 

******************************************************* *******************************************************