How to power up all ONTAP nodes in a cluster following a graceful shutdown
Applies to
- ONTAP 9
- AFF models
- FAS models
- Excluding MetroCluster
Description
Several events might require a graceful shutdown of ONTAP equipment such as:
- Scheduled site power outage
- Data center wide maintenance
- Physical system move
- Preparation for future re-purposing of equipment
This article will assist you in the powering up your equipment.
Prerequisites |
|