Will the upcoming Azure maintenance impact the CVO/Connector

Views:
100
Visibility:
Public
Votes:
0
Category:
cloud-volumes-ontap-cvo
Specialty:
cloud
Last Updated:

Applies to

  • Cloud Volume ONTAP (CVO)
  • Microsoft Azure
  • BlueXP Connector

Answer

  • There are multiple EventType of maintenance on Azure as below:
    • Freeze: The Virtual Machine is scheduled to pause for a few seconds. CPU and network connectivity may be suspended, but there's no impact on memory or open files.
    • Reboot: The Virtual Machine is scheduled for reboot (non-persistent memory is lost). In rare cases a VM scheduled for EventType:"Reboot" may experience a freeze event instead of a reboot. Follow the instructions above for how to know if the event is complete and it's safe to restore your workload.
    • Redeploy: The Virtual Machine is scheduled to move to another node (ephemeral disks are lost).
    • Preempt: The Spot Virtual Machine is being deleted (ephemeral disks are lost). This event is made available on a best effort basis
    • Terminate: The virtual machine is scheduled to be deleted.
  • The Azure maintenance could lead to a temporary access limit for BlueXP Connector and Single CVO

So, if the upcoming Azure maintenance has been notified and can't be determined it's EventType, it recommends scheduling a maintenance window to complete it to avoid impact happening.

Additional Information

Example mail notification from Azure:

Dear Azure customer,
 
One or more Azure Virtual Machines (VMs) associated with your subscription require a maintenance update to migrate these VMs to newer hardware. While the vast majority of platform maintenance causes no interruption to your services, this update will require a reboot .
 
This maintenance has two phases: the self-service phase and a scheduled maintenance phase.
 
Azure Service Health provides you with the current status of each VM that requires maintenance and allows you to initiate the self-service maintenance proactively – any time between now and October 02, 2024 (23:59 UTC). If self-service maintenance has not been completed by then, Azure will automatically initiate maintenance on any VM that still requires it, sometime between October 03, 2024 (00:00 UTC) to October 09, 2024 (23:59 UTC). This scheduled maintenance will be performed one

NetApp provides no representations or warranties regarding the accuracy or reliability or serviceability of any information or recommendations provided in this publication or with respect to any results that may be obtained by the use of the information or observance of any recommendations provided herein. The information in this document is distributed AS IS and the use of this information or the implementation of any recommendations or techniques herein is a customer's responsibility and depends on the customer's ability to evaluate and integrate them into the customer's operational environment. This document and the information contained herein may be used solely in connection with the NetApp products discussed in this document.