Issue

  • After power cycle of a switch, filers reporting ISL down

The cable used to connect switch "CN1610-1/ Link Aggregate 1" to the ISL port might be faulty. For port-channel, please check each individual link.
The cable used to connect switch "CN1610-1/Slot: 0 Port: 13 10G - Level" to the ISL port might be faulty. For port-channel, please check each individual link.
The cable used to connect switch "CN1610-1/Slot: 0 Port: 14 10G - Level" to the ISL port might be faulty. For port-channel, please check each individual link.
The cable used to connect switch "CN1610-1/Slot: 0 Port: 15 10G - Level" to the ISL port might be faulty. For port-channel, please check each individual link.
The cable used to connect switch "CN1610-1/Slot: 0 Port: 16 10G - Level" to the ISL port might be faulty. For port-channel, please check each individual link.
The cable used to connect switch "CN1610-2/ Link Aggregate 1" to the ISL port might be faulty. For port-channel, please check each individual link.

 

 

CUSTOMER EXCLUSIVE CONTENT

Registered NetApp customers get unlimited access to our dynamic Knowledge Base.

New authoritative content is published and updated each day by our team of experts.

Current Customer or Partner?

Sign In for unlimited access

New to NetApp?

Learn more about our award-winning Support